spacer
spacer
spacer
News
News
2012 Green Gardener Classes spacer spacer spacer

This Continuing Education/Advanced Series of the Monterey Bay Green Gardener Certification Program offers professional development and practical training in ecological landscaping methods, with a special emphasis on low-impact development (LID) practices that conserve water and energy and reduce pesticide, nutrient, and sediment non-point source pollution from urban landscapes. The target audience of the Green Gardener advanced series include Green Gardener alumni, landscape industry professionals, those aspiring to work in the landscape industry, and the general public with an interest in ecological horticulture.

Click here to view the 2012 Green Gardener Class schedule. The City of Watsonville along with Ecological Landscaping Association, California Landscape Contractors Association, City of Santa Cruz, Scotts Valley Water District and Soquel Creek Water District are proud sponsors of the 2012 Green Gardener Classes.

 
Street/Road Repairs spacer spacer spacer

UPDATE - FREEDOM BLVD. RECONSTRUCTION PROJECT

UPDATE - GREEN VALLEY RD. RETAINING WALL PROJECT

 

 

"Photos courtesy of Tarmo Hanula - Register Pajaronian"

 

CURRENT UPDATE (3/20/2012)

Roadwork on Freedom Blvd. is nearing completion. Striping has been completed and signage will be installed this week (3/19/2012). All that remains to be done after this is some minor concrete work on the Lincoln Street island and some minor corrections.

 

All work should be done by the end of this month (March).

 

UPDATE (2/2012) 

The anticipated completion date has been extended to April 2012. Remaining work includes completion of the Freedom Boulevard and Lincoln Street intersection and reconstruction of spacer Freedom Boulevard between East High Street and Broadis Street.

 

The City expresses appreciation to the Freedom Boulevard residents, businesses and travelers that pass through the construction area regularly. The project has been delayed for the following reasons:

 

Additional improvements have been added to the project. Initially, the project included replacement of curb, gutter and sidewalk and reconstruction of the Freedom Boulevard from East high Street to Broadis Street. The City expanded the project scope to include more of Stanford Avenue and the intersection of Freedom Boulevard and Lincoln Street. The work at Lincoln Street will improve pedestrian safety and add landscaping. These additions have required more time.

 

Unforeseen circumstances have increased the time to complete the project. These include poor soils in some locations that required removal, replacement and additional compaction. There have also been abandoned utilities that were not found until excavation took place and could not be addressed until the utility companies identified them and said that they could be removed. When the work extended into the holiday season, the City directed the contractor to reschedule work to minimize the impact on local businesses.

 

Additional time was lost as the contractor had difficulty scheduling subcontractors. The most recent delay has come about because of a poor paving job at the Freedom Boulevard and Lincoln Street intersection. The City has required that the contractor remove the substandard paving and has asked the contractor to determine the cause of the paving problem and propose corrections before resuming work.

 

WHAT'S NEXT?

After the Freedom Boulevard Reconstruction project is completed, the City will begin discussions with the electric, telephone and television companies to remove the existing overhead wires and install them in the underground conduit and boxes that were installed recently. This is known as a "Rule 20A Project" and will take three to five years to plan and design. Not only are the utility poles and wires in the street removed, but the service connections from the street to the buildings are changed from overhead to underground. This will require coordination between the City and the individual property owners and tenants.  If you have any questions regarding this project, please contact Murray Fontes at 831-768-3117.

 

 

GREEN VALLEY RD. RETAINING WALL PROJECT

CURRENT UPDATE (3/20/2012)

Construction is nearing completion. This week, (3/19/2012) the Contractor will spacer finish installing signs and will place concrete in the area between the wall and the existing sidewalk. This should be completed at the end of this month (March).

 

In April, work will begin on a mural to be painted on the face of the wall by local artist Arturo Thomae and two student artist interns. The mural will be a slough scene and will be completed in approximately 3 months.

 

 

UPDATE (2/2012)

Construction of the Green Valley Road Retaining Wall project is currently under way and should be complete by the end of March. The wall is on the west side of Green Valley Road between Main Street/Stake Route 152 and Melwood Way. One lane of traffic on south Green Valley Road at the project location will be closed at times to allow access by construction vehicles.   After the wall is complete, it will be allowed to cure for a month and then a mural of slough scene will be painted on the face. For additional information on this project you can call Murray Fontes at 768-3117.

 

 

 

 

CALTRANS-ROAD PROJECTS IN THE AREA

 

CALTRANS-Salinas Road Interchange Projectspacer

CALTRANS-Prunedale Improvement Projects

CALTRANS-Highway 1 Soquel to Morrissey

CALTRANS-Highway 1 & 17 Interchange Project

CALTRANS-Road Information Update

CRUZIO Traffic Information

 

 
Rodriguez Street Sewer Replacement spacer spacer spacer

spacer The City of Watsonville has contracted The Don Chapin Company to construct a new sewer line on Rodriguez Street between 1st Street and extending across Riverside Drive (Highway 129). The project is scheduled to start Monday, March 5, 2012 and completed in approximately 2 weeks.

 

During construction, Riverside Drive traffic will be accommodated with a lane in each direction. Periodically left and right turns from Riverside Drive to Rodriguez Street will be prohibited. Rodriguez Street will at times be closed between 1st Street and Riverside Drive.

 

 

 

 
More...
  • Toilet Replacement & Rebate Program
<< Start < Prev 1 2 3 Next > End >>

Results 1 - 4 of 10
Monthly Video Highlight
gipoco.com is neither affiliated with the authors of this page nor responsible for its contents. This is a safe-cache copy of the original web site.