Dream Chaser’s Development Schedule

Posted
by
Doug Messier
on April 20, 2011, at 10:52 am
in News
. Tags: CCDev, Dream Chaser, NASA, Sierra Nevada Corporation.
Comments: no responses
Comments
spacer

SNC Dream Chaser docks with the International Space Station. (Credit: Sierra Nevada Corporation)

So, what is Sierra Nevada Corporation going to do with the $80 million it’s receiving from NASA under the CCDev program? The following schedule provides a great overview of how the company will develop its Dream Chaser (DC) spacecraft over the next 13 months.

Appendix 2(a). CCDev2 Performance Milestones and Success Criteria.
Baseline Milestones Milestone
Value
Baseline $80M
Award
Schedule
Milestone 1: System Requirements Review 

Description: Conduct System Requirements Review (SRR); SNC shall present a briefing of the system requirements for the Dream Chaser Space System (DCSS). SNC shall provide NASA a hard copy of the presentation materials and responses to NASA questions concerning system requirements.

Success Criteria: Meet criteria specified in the SNC System Requirements Review Entrance and Success Criteria. (Table 1)

spacer May
2011
Milestone 2: Canted Airfoil Fin Selection 

Description: Complete wind tunnel tests and Computational Fluid Dynamics (CFD) analysis on candidate airfoil fin Outer Mold Line (OML) and select final fin shape to ensure proper aerodynamic performance of fins. Present analysis results and final DC airfoil shape to NASA.

Success Criteria: Completion of the review of the airfoil selection as described above. (Table 2)

spacer June
2011
Milestone 3: Cockpit Based Flight Simulator 

Description: Complete fabrication and assembly of cockpit structure, install simulator displays and controls, and conduct a Simulator Readiness Review to verify readiness for engineering and pilot evaluations.

Success Criteria: Meet the criteria specified in the SNC Simulator Readiness Review Entrance and Success Criteria. The DC cockpit structure is completed, simulator hardware integrated, and the simulator is ready for engineering simulations. (Table 3)

spacer July
2011
Milestone 4: Vehicle Avionics Integration Laboratory 

Description: Vehicle Avionics Integration Laboratory (VAIL) designed and ready to begin DC avionics developmental engineering tests. VAIL will allow testing, verification and validation of avionics and software.

Success Criteria: Demonstration of a functional VAIL, which is ready for avionics bench testing. (Table 4)

spacer September
2011
Milestone 5: System Definition Review 

Description: Conduct System Definition Review (SDR); SNC shall present a briefing of the proposed Dream Chaser Space System architecture/design. SNC shall provide NASA a hard copy of the presentation materials and responses to NASA questions concerning system definition.

Success Criteria: Meet criteria specified in the SNC System Definition Review Entrance and Success Criteria. (Table 5)

spacer October
2011
Milestone 6: Flight Control Integration Laboratory 

Description: Flight Control Integration Laboratory designed, developed and ready to begin developmental engineering tests of flight control actuators and surfaces. Complete assembly of the Flight Control Bench Test hardware such that it is ready to support ETA flight control tests.

Success Criteria:
Demonstration of a functional Flight Control Integration Laboratory which is ready for flight control bench testing. (Table 6)

spacer November
2011
Milestone 7: ETA Structure Delivery 

Description: Complete assembly of and deliver the ETA primary structure for start of system integration and installation of secondary structure.

Success Criteria: Assembly and delivery of the ETA primary structure; ready for system integration. (Table 7)

spacer December
2011
Milestone 8: Separation System Test 

Description: Complete design and construction of prototype DC separation system and demonstrate activation to validate concept and verify performance of separation system.

Success Criteria: Demonstration of the DC prototype separation system test as described in the test plan. Table 8

spacer

February
2012

Milestone 9: Preliminary Design Review 

Description: Conduct Preliminary Design Review (PDR). SNC shall present a briefing of the preliminary Dream Chaser design. SNC shall provide NASA a hard copy of the presentation materials and responses to NASA questions concerning system preliminary design.

Success Criteria: Meet criteria specified in the SNC Preliminary Design Review Entrance and Success Criteria. (Table 9)

spacer May
2012
Be Sociable, Share!
  • spacer
spacer
  • Tweet

Permalink

Post Comment

0 Responses to “Dream Chaser’s Development Schedule”

Feed for this Entry Trackback Address

  1. No Comments

Leave a Reply


gipoco.com is neither affiliated with the authors of this page nor responsible for its contents. This is a safe-cache copy of the original web site.