Indian Truck Trail Interchange

Reconstruct and widen existing I-15/Indian Truck Trail interchange and ramps

  • Overview
  • Construction Activities
  • Photos

Contractor All American Asphalt
Construction Start February 2012
Construction Completion February 2013
Work Hours Monday – Friday 7 AM – 6 PM
Some weekend work, which includes occasional ramp and road closures, is anticipated.
Project Helpline (877) 221-1472

Project Improvements

  • Widen Indian Truck Trail to four lanes with dedicated left and right-turn lanes from just west of the interchange to Temescal Canyon Road.
  • Install a sidewalk on the south side of Indian Truck Trail.
  • Construct walls under the I-15 bridges.
  • Add three new traffic signals at the SB and NB I-15 / Indian Truck Trail ramp intersections, and at the intersection of Indian Truck Trail / Temescal Canyon Road.
  • Add ramp meters on I-15 NB and SB on-ramps.
  • Reconfigure and construct the intersection of Indian Truck Trail and Temescal Canyon Road.

Click map to zoom in
spacer

Construction Activities

1/28/2013
 
Indian Truck Trail Off-Ramp Closures
 
The northbound and southbound I-15 off-ramps at Indian Truck Trail will be closed at the following times on the dates shown below. The purpose of these closures is to allow for paving.
 
February 1 to February 4, 2013

Northbound off- ramp 10:00 p.m. – 4:00 a.m.

Southbound off- ramp 11:00 p.m. – 5:00 a.m.

 
 
 
 
01/17/2013

Indian Truck Trail Ramp Closure
When:  January 22 – January 24
Northbound on/off ramps  8:00pm – 4:00am
Southbound on/off ramps 9:00pm – 5:00am
Where:  Temescal Valley:  Indian Truck Trail Road

12/17/2012
 
Paving Schedule:
 
S/B on-ramp paving schedule
 
Tuesday 12/18/12: Spray SC-70 prime coat
Wednesday 12/19/12: prime coat cure
Thursday 12/20/12 at 07:00: pave HMA-A, install traffic control then open the ramp for traffic as scheduled at 21:00 (09:00 PM),
 
 
N/B & S/B off-ramps HMA-A-Bond Breaker paving schedule:
 
Thursday 12/20/12: right after finish paving the S/B on-ramp, pave HMA-A-Bond Breaker at the N/B & S/B off-ramps section atop the lean concrete base, Inspections, lab, and third-party lab works shall be coordinated per the above schedule.

 

12/11/2012

UPDATED: Indian Truck Trail Ramp Closures Beginning Nov 26

Construction crews will be performing closures on the I-15 on and off-ramps at Indian Truck Trail beginning November 26. These closures are part of the Indian Truck Trail Interchange Project. Please click the links below for details.

Ramp Closure Details (English)

Ramp Closure Details (Spanish)

 

8/30/12


Temescal Canyon Road is NOW OPEN.

 

Northbound Temescal Canyon Road Closure

Northbound Temescal Canyon Road will be closed July 20, 2012 through late September 2012.   The Closures will include the Intersection at Temescal Canyon Rd and Indian Truck Trail and Northbound Temescal Canyon Rd between Corona Lake entrance and Campbell Ranch Rd.  Click on the maps below for detour information.