On July 11, 2012, the DOE Office of Science granted CD-1 approval to Mu2e. Most recently (March, 2015) the DOE granted CD-2 approval to baseline the experiment and CD-3b approval for the ground breaking of our experimental hall. A DOE CD-3a approval for the procurement of our superconducting cable occured in July, 2014. We are now working towards DOE CD-3c approval.
The Technical Design Report can be found here. here.--->
The May 2014
Report of the Particle Physics
Project Prioritization Panel (P5) recommended that the Mu2e project be completed under all funding scenarios. See Table 1, page 17, and
Recommendation 22, page 15.
Date | Action | |
---|---|---|
March 4, 2015 | Approval of CD-2/3b by Office of Science Director Dehmer | |
July 11, 2014 | Approval of CD-3a by Office of Science Director Dehmer | |
May 22, 2014 | Strongly endorsed by P5 2014 [cf pg 15]. | |
July 11, 2012 | Approval of CD-1 by Office of Science Director Brinkman | |
May 5, 2011 | Sucessful Completion of Internal Design Review (pre CD-1 review). | |
November 24, 2009 | Received CD-0 from DOE Office of Science. | |
November 21, 2008 | Stage I approval granted by Fermilab directorate, following recommendation from PAC. | |
May 29, 2008 | Strongly endorsed by P5 2008 [see page 43]. |