Feb04
2012
Leave a Comment spacer Written by Mike Caspar

I recently had a revelation about the Title “Scrum Master” and why it seems to be so confusing in some companies, especially those that are moving from Command and Control to an Agile Environment.

I was observing the activities of a new team that did not have a Scrum Master but were trying to use the SCRUM Framework. The company had unfortunately not added this role in their new SCRUM team(s). The reasons why are not important. Let’s just say, they now have those roles.

When the Scrum Master was selected, some issues showed up over a perception of that person getting a “promotion” to a management type position. They were now the “Master of the Team” (or so the perception was).

I managed to help that team out by simply reminding them the intention is that the Scrum Master role is as a Master of SCRUM, not a Master of the Team.

There are some management type abilities to be a Scrum Master for sure, but they are more directed to interfacing with the outside world and removing obstacles for the team. There are some management skills required to be able to have the confidence to keep the rules of Scrum and push back and deal with different levels within the organization.

Remember, the word is SCRUM Master, not TEAM Master, Team lead, Project manager, etc.

Of course, changing the order of the words would be inappropriate, but perhaps explaining the distinction to others might help clear up some of the confusion for your teams.

The term is SCRUM Master

Mike Caspar

Posted in How-To Apply Agile, Scrum, XP and Lean, Theory of Agile - Tagged agile adoption, scrum, scrum master

Important Words about Scrum and Tools

Jan17
2012
4 Comments spacer Written by Mishkin Berteig

Ken Schwaber, the founder of Scrum, has a blog.  In it, someone mentioned that Scrum is changing.  Ken responded:

If you change the Scrum framework you just simply aren’t using Scrum and are probably canceling some of its most important benefits.

Thank you Ken!  I wholeheartedly agree.  Every CSM class I teach, I emphasize the complete nature of Scrum as a single tool, not a collection of tools.  Learning Scrum is about learning the tool, not learning how to pick and choose pieces of a tool.  Let’s explore this metaphor of Scrum as a tool.

Consider a hammer.  A hammer is ideally suited for pounding nails into wood.  It has two parts: a head and a handle.  If you take the parts and use them separately, they can still be used for pounding nails into wood… but they are very ineffective compared to the hammer (although better than using your bare fist).  It is non-sensical to decompose the hammer and try to use the pieces separately.  However, a hammer is not suited to other purposes such as driving screws or cutting wood.  It’s perfection is not just in its form, but also in its proper application.  A hammer works through a balanced combination of leverage and momentum.

Scrum is like a hammer.  It has parts (daily Scrum, Sprints, ScrumMaster, etc.), but taking the parts and trying to use them separately is… you guessed it… non-sensical.  The parts of Scrum combine to be an extremely effective tool for new product development.  Just like a hammer, there are things you wouldn’t want to do with Scrum such as manufacturing or painting a wall.  (We might not all agree on the limits of the use of Scrum… that’s something for another article.)  Scrum works through a combination of pressure on the organization and “inspect and adapt” (continuous improvement).

Please.  Don’t modify Scrum.  If you must change things about Scrum, please stop calling it Scrum.

Posted in Scrum, XP and Lean, Theory of Agile - Tagged Continuous Improvement, ken schwaber, organization, scrum

Interesting: Anecdote, Evidence and Research

Jan11
2012
Leave a Comment spacer Written by Mishkin Berteig

Dave Nicolette has written a fascinating rant called “All evidence is anecdotal” in reference to research about software engineering.

Posted in Links to Agile Info - Tagged agile, engineering, research, software

Interesting: Stoos Network

Jan10
2012
Leave a Comment spacer Written by Mishkin Berteig

Transforming organizations: check out the Stoos Network.  Wish I had been there!  Some of my favourite people were there!

Posted in Agile Management, Announcements, Links to Agile Info - Tagged management, Stoos, Work

Seven Options for Handling Interruptions in Scrum and Other Agile Methods

Jan08
2012
4 Comments spacer Written by Mishkin Berteig

Almost three years ago we wrote a brief article about interruptions.  In that article, we described four methods of dealing with interruptions.  I would like to expand on those four methods and add three more to present a comprehensive set of options for organizations struggling with this.

Option One: Follow Scrum Strictly

The rules of Scrum are clear: if it isn’t part of the team’s work for a Sprint, then it shouldn’t be done.  From the moment the team commits to work in Sprint Planning to the end of the Sprint with the Sprint Review, the team needs to be protected from interruptions.  If an interruption is truly urgent enough to warrant the team’s attention mid-Sprint, then the Sprint can be canceled.  This is a pretty extreme result however since it invalidates the team’s previous commitment.

spacer

 

The Scrum approach is based on the basic philosophy that Scrum is a system to expose the problems and obstacles in the organization.  This is painful!  In the case of interruptions, Scrum then is metaphorically throwing them back in the face of the organization and saying “this is bad behavior!  Fix the behavior that causes so many interruptions, don’t find a way to accommodate interruptions.”

For example, many teams are faced with interruptions related to their support of the software they are creating.  In Scrum, deflecting the interruptions forces the team and the organization to examine the root causes of the support issues and fix them.  If the team is producing software with lots of defects, then that needs to change.  If the team is producing software that is hard to use, then that needs to change.  If the team is producing software without the appropriate level of user documentation, then that needs to change.  But what doesn’t change is the team breaking the safety of the Sprint defined by the rules of Scrum.

Option Two: Allocate a Portion of Time to Interruptions

Given certain conditions, the amount of interruption of a team can be “stable”. If this is the case, then the team can reasonably set aside a certain percentage of their time to handle interruptions. Determining if this is possible can be done by tracking the occurrence of interruptions and the level of effort to handle them.

spacer

In a team using this method, there are two ways to allocate this time: everyone on the team gives a certain amount of time each day to handling interruptions OR one or two people on the team are committed full-time for a cycle to handling interruptions. In either case, if the amount of actual time spent on interruptions is less than the amount of time available, then that difference of time must be used carefully. Generally, the best use of this extra time is to work on resolving the root causes of interruptions. For example, if one person of a team is dedicated to dealing with interruptions, and most interruptions come from in-the-field bug support requests, then that person might spend any extra time working on fixing older lower-severity defects.

The amount of time that the team is allocated to handling interruptions should never be exceeded otherwise the team’s commitments at the start of the cycle are not really commitments.

This option is by far the most common systematic approach to dealing with defects

Option Three: Visible Negotiation of Change

Another common method of handling interruptions is the “fluorescent note card” method which requires visible stakeholder negotiation around the impact of interruptions. With this method, any time a stakeholder comes to the team with an interruption request, the ScrumMaster/Coach/Process Facilitator writes the request on a bright colored note card so that it is easy to distinguish it from the other tasks the team is working on in their current cycle.   The ScrumMaster then asks the team to do a task breakdown on the card and using their normal process (whatever that is) estimates the work effort. The requesting stakeholder then has to negotiate with any other stakeholders (and in particular the Product Owner/Growth Facilitator about what work to remove from the iteration in order to make room for the new work. This process works well primarily because it makes the tradeoffs visible. It does not work so well with letting the team make and keep their commitments which can have a long-term impact on trust.

spacer

This approach requires a few things to be in place to be effective:

  1. A visible task board instead of electronic tools for task tracking.  The visibility makes the change much more immediate and you must have the stakeholders involved right in the same physical space.  An electronic tool makes this too abstract and can lead to some important stakeholders not being properly aware of changes.
  2. A team that is reasonably good at estimating.  By “good” I mean both accurate and fast.  If it takes the team half an hour to do an accurate estimate, then that is already a significant interruption in itself!  A team should be able to look at an interruption, break down the tasks and come up with a reasonably accurate estimate within no more than 10 minutes.  Remember that doing this is already task switching so there is going to be an additional cost to the team.
  3. Finally, and perhaps most importantly, a clear agreement must be in place among stakeholders that this approach to interruptions is allowed and that the consequence of it is that the team cannot be held accountable for their commitments!!!  I cannot stress this enough!

Option Four: Separate Team for Interruptions

This option is fairly self-explanatory and in fact is just a way of saying that you have a separate support group who deals with interruptions.  The more technically capable this group is, and the more authority they have to make changes to the code/database/etc., the more effective they will be at protecting the agile teams from interruptions.

spacer

In some ways, this is a good approach because it makes the cost of interruptions very visible to the business: how much does your support team cost?  If this cost is growing, then it means that the development teams are creating software that is harder and harder to support.

If you follow this approach, please ensure that you do not rotate development team members through the support team as this damages the team-building process for both the development team and the support team.

(One radical option to try as an add-on to this is to defray the cost of this support team by tying developer’s salaries to the cost of support.  To make this palatable, you might simply say to the development team that any time a support person can be laid off due to improved quality in the product/system, that person’s salary will be permanently distributed and added as a raise to the salaries of the development folks.  PS.  I’ve never seen any organization do this – it’s just a theory.)

Option Five: Extremely Short Cycles

A less common, but interesting method for handling interruptions is to have extremely short iterations. In this method, choose your iteration length to be so short that you can always start work on urgent interruptions before anyone gets impatient! This can be exhausting, but it is one of the best ways to get the team and the organization to understand the large toll that these interruptions take.

spacer

There is a simple way to determine how long your cycle should be based on measurement.  Choose a “normal” duration (e.g. one or two weeks) and for several cycles track how many interruptions are submitted to the team, and how urgent is the turn-around time on those interruptions.  After several cycles, the team can then adjust its cycle length so that, on average, the team is able to start and finish a cycle in a time shorter than the expected frequency of interruptions.

For example, one team I worked with found that in general, they were getting interruptions that needed to be handled within three or four days, but more urgent interruptions were rare.  They decided to use a cycle that was only two days long so that on average they would complete handling an interruption in three days.  (Interruption comes half way through a cycle and is put on the backlog at the top.  The next cycle they start and finish the interruption.  Elapsed time is three days.)

Option Six: Status Quo / Suffering

There is nothing inherently wrong with continuing with your current approach to handling interruptions.  It probably makes some people miserable, but there are also some people who really enjoy crisis and constant change.  In fact, it may be part of the culture of your organization or something that is strategically important in your particular industry.  That doesn’t mean you can’t be agile, but it may mean that you are making compromises where you are trading off team performance for some other benefit.  it is important that if you choose to continue with your status quo, that you make the trade-off transparent.  Tell everyone on your teams exactly why you are making the trade-off and what is the expected benefit of doing so.

spacer

Option Seven: Commitment Velocity

The most sophisticated option is based on measuring a special kind of velocity called “Commitment Velocity”.  This is a mechanism that allows both interruptions to be handled mid-cycle and for teams to make commitments that they can keep.  In the simplest terms, Commitment Velocity is the minimum historical slope of a team’s Sprint burndown.

spacer

For example, if a team in Sprint 1 has 240 units of effort at the start of the Sprint, but, partly due to interruptions, does not finish and then has 40 units of effort left unfinished at the end of the Sprint, then the Commitment Velocity (slope) of the team is 240 – 40 = 200.  In their next Sprint planning meeting, they would plan such that they had at most 200 unites of effort in their Sprint plan.  The team then does their second Sprint and again, partly due to interruptions, they don’t finish everything.  Perhaps this second sprint started with 195 units of effort (<200) and finished with 10 units of effort remaining.  Their new Commitment Velocity is 195 – 10 = 185.  They do a third sprint, but they finish everything.

It is tempting for the team to perhaps take an average – maybe they finished 200 units of effort in their third Sprint so they average 200, 185 and 200 leaving 195.  This is not Commitment Velocity.  By definition, an average means that the team will successfully complete all their work 50% of the time.

Instead, the team maintains its Commitment Velocity of 185 for their fourth Sprint.  By the law of large numbers and the central limit theorem, as the team uses this tool of Commitment Velocity for more and more Sprints, eventually their ability to keep their commitments, even with interruptions) will become closer and closer to 100% certain.

Selecting an Option

Ultimately, the most important thing in selecting one of these options is to do so consciously and in the spirit of learning that underlies agile methods.  Choose  an option and then stick with it long enough to truly understand if it is working for you or not.

There are some things to consider as well:

  • If you are trying to do a dramatic improvement in how your organization gets stuff done, I would recommend choosing either Option One (Follow Scrum Strictly) or Option Seven (Commitment Velocity).  Both of these are options that put pressure on the team and the organization to improve.
  • If you don’t have strong executive support for Agile, then probably Options Two (Time Allocation), Four (Separate Team) and Five (Short Cycles) are going to be your best bet at first.
  • If you do have strong executive support, but you aren’t desperate to improve your organization, you might consider Option Three (Visible Negotiation).
  • Of course, Option Six (Status Quo) is the easiest… I don’t really recommend it though!  Agility requires systematic change to encourage continuous improvement.  All the other options assist with this.
Posted in How-To Apply Agile, Scrum, XP and Lean, Theory of Agile - Tagged agile, commitment, disruptions, interruptions, management, scrum, support, urgent work, velocity

Evolution of Agile Methods

Jan05
2012
Leave a Comment spacer Written by Mishkin Berteig

I had the great honour of participating in two sessions of David Sabine’s excellent “Agile Questions” show – check it out!

Show One: “Should/can agile methods be blended?”

Show Two: “As Scrum teams evolve, do they become OpenAgile?“